Metal Support Beams
Outside Kitchen & Terrace
Vlado, Stefan & I in a Meeting
Terrace Paving & Sitting Area
Reconstruction Of Terrace
The stonemasons will rebuild it to make it structurally much stronger to support the large stone sitting area I have designed.
Garage Looking Really good
It looks perfectly hunkered down into the landscape as if it has always been there, which is exactly what I wanted when I designed it.
To put the scale of this wall and garage in perspective - The wall is 33.5m long with a maximum height of 4.6m. The garage and storage room are 10m wide and 4.2m high.
Construction Of Garage Roof
Over the last three days the garage timber for the finish ceiling has been fitted to lay on the joists, next the roof membrane and last the insulation.
All that is left to do now is the roof tiles and fitting the Velux window over the storage room.
Garage Walls Completed
All the stone walls of this garage are now completed and the finished garage now measures 9.9m long x 6.5m wide and 4.6m high at the back wall.
Pruning Olive Trees
Bojan an olive tree expert is hard pruning the four olive trees, in readiness for them being dug up and transported from Ulcinj near the Albanian border to my villa on Luštica, which is 108 km.
Stefan & Vlado Celebrating
Stefan and Vlado are celebrating the fact they are able to officially come back to work, because all Covid pandemic restrictions have now been lifted.
This team of builders managed to work quite a lot over Covid in Montenegro, which has not been the case in the UK.